AS CELIK FACTORY
ESKISEHIR - TURKEY
all electrical work
The electrical works of AS Celik Factory, the factory of a steel compony located in Eskisehir, has been done by TR Engineering
Employer: AS CELIK A.S.
Contractor :-
Date Of Commencoment: 01.06.2010
Date Of Completion: 15.10.2010
Finished Works : 0.4 KV power distrubition Lighting system,Fire alarm system,Emergeny announcement system, Security system.CCTV system,Grounding connection system.Lightning protection system Total Power:-
Total Power: 13,8/154 Kv 3x 38 MVA
GULLUBAG HEPP
GULLUBAG - TURKEY
HEPP Project
Güllübağ HEPP Project Electrical Primary and Secondary Erection Works Field Test and Commissioning Works
Employer: SENERJİ ENERJİ ÜRETİM A.Ş.
Contractor: Areava T&D Energy Industry Inc.
The work done
3 Feeders 154/13.8 KV O.G. Primary and secondary electrical assembly, field testing and commissioning works of switchgear systems
Power: 13.8/154 KV 3 MVA
KHABAROVSK REFINERY PROJECT
RUSSIA
all electrical work
Contractor: Enka İnşaat A.Ş
Employer: Tecnicas Reunidas Finished Works: All electrical and instrumental works of hydrocracker and hydrogen area.
Date Of Commencement: 01.08.2012
Date Of Completion: 31.06.2013
SÜLEYMANİYE 1500 MW COMBINED CYCLE POWER PLANT
SULAIMANIA - IRAQ
all electrical work
Electrical & Instrumental installations works of 1500 MVA.
Employer:MASS GROUP HOLDING
Contractor: ENKA INŞAAT A.S.
Date Of Commencement: 12.05.2014
Date Of Completion: 31.03.2016
Finished Works: Electrical & Instrumental installations works of 1500 MVA Sulaymaniyah Combined Cycle Power Project in Suleymaniyah, Iraq
BAZYAN COMBINED CYCLE POWER PLANT
SULAIMANIA - IRAQ
all electrical work
Electrical and instrumentation installations works at 500 MVA.
Employer: QUAIWAN COMPONY GROUP
Contractor : ENKA INŞAAT A.S.
Date Of Commencement: 15.03.2015
Date Of Completion: 31.12.2015
Finished Works: Electrical & Instrumental installations works of 500 MVA Bazyan Combined Cycle Power Plant Project in Suleymaniyah, Iraq
DHIQAR 750MW COMBINED CYCLE PLANT
DHIQAR - IRAQ
all electrical work
All electrical and instrument montage works of the plant.
Employer: Ministry of Electricity of Iraq
Contractor: ENKA İnşaat ve Sanayi A.Ş. & General Electric
Finished Work: All electrical works.
Total Power: 750 MW
SAMAWA 750MW COMBINED CYCLE PLANT
SAMAWA - IRAQ
all electrical work
All electrical and instrument montage works of the plant
Employer: Ministry of Electricity of Iraq
Contractor: ENKA İnşaat ve Sanayi A.Ş. & General Electric
Finished Works: All electrical works.
Total Power: 750 MW
SUMGAIT HIGH DENSITY POLYPROPYLENE PROJECT
SUMGAYT - AZERBAIJAN
all electrical work
Employer: SOCAR - Azerbaijan
Contractor: Kinetics Tecnimont -– Italy
Date Of Commencoment : 01.06.2017
Date Of Completion: 30.10.2018
Finished Works: All electrical and instrument montage Works