AS CELIK FACTORY

ESKISEHIR - TURKEY

all electrical work

 

The electrical works of AS Celik Factory, the factory of a steel compony located in Eskisehir, has been done by TR Engineering

Employer: AS CELIK A.S.

Contractor :-

Date Of Commencoment: 01.06.2010

Date Of Completion: 15.10.2010

Finished Works : 0.4 KV power distrubition Lighting system,Fire alarm system,Emergeny announcement system, Security system.CCTV system,Grounding connection system.Lightning protection system Total Power:-

Total Power: 13,8/154 Kv 3x 38 MVA


GULLUBAG HEPP

GULLUBAG - TURKEY

HEPP Project


Güllübağ HEPP Project Electrical Primary and Secondary Erection Works Field Test and Commissioning Works

Employer: SENERJİ ENERJİ ÜRETİM A.Ş.
Contractor: Areava T&D Energy Industry Inc.

The work done

3 Feeders 154/13.8 KV O.G. Primary and secondary electrical assembly, field testing and commissioning works of switchgear systems

Power: 13.8/154 KV 3 MVA

 

KHABAROVSK REFINERY PROJECT

RUSSIA

all electrical work

 

Contractor: Enka İnşaat A.Ş

Employer: Tecnicas Reunidas Finished Works: All electrical and instrumental works of hydrocracker and hydrogen area.

Date Of Commencement: 01.08.2012

Date Of Completion: 31.06.2013



SÜLEYMANİYE 1500 MW COMBINED CYCLE POWER PLANT

SULAIMANIA - IRAQ

all electrical work

 

Electrical & Instrumental installations works of 1500 MVA.

Employer:MASS GROUP HOLDING

Contractor: ENKA INŞAAT A.S.

Date Of Commencement: 12.05.2014

Date Of Completion: 31.03.2016

Finished Works: Electrical & Instrumental installations works of 1500 MVA Sulaymaniyah Combined Cycle Power Project in Suleymaniyah, Iraq

 

BAZYAN COMBINED CYCLE POWER PLANT

SULAIMANIA - IRAQ

all electrical work

 

Electrical and instrumentation installations works at 500 MVA.

Employer: QUAIWAN COMPONY GROUP

Contractor : ENKA INŞAAT A.S.

Date Of Commencement: 15.03.2015

Date Of Completion: 31.12.2015

Finished Works: Electrical & Instrumental installations works of 500 MVA Bazyan Combined Cycle Power Plant Project in Suleymaniyah, Iraq



DHIQAR 750MW COMBINED CYCLE PLANT

DHIQAR - IRAQ

all electrical work

 

All electrical and instrument montage works of the plant.

Employer: Ministry of Electricity of Iraq

Contractor: ENKA İnşaat ve Sanayi A.Ş. & General Electric

Finished Work: All electrical works.

Total Power: 750 MW

 

SAMAWA 750MW COMBINED CYCLE PLANT

SAMAWA - IRAQ

all electrical work

 

All electrical and instrument montage works of the plant

Employer: Ministry of Electricity of Iraq

Contractor: ENKA İnşaat ve Sanayi A.Ş. & General Electric

Finished Works: All electrical works.

Total Power: 750 MW



SUMGAIT HIGH DENSITY POLYPROPYLENE PROJECT

SUMGAYT - AZERBAIJAN

all electrical work

 

Employer: SOCAR - Azerbaijan

Contractor: Kinetics Tecnimont -– Italy

Date Of Commencoment : 01.06.2017

Date Of Completion: 30.10.2018

Finished Works: All electrical and instrument montage Works